  • Date

  • Equipment I.D#

  • Location

  • Crew Member

  • Supervisor

  • Document run hours.

  • completed every 1000 to 2000 hours test drain valve(s) and clean strainer(s).

    • Pass
    • Flag
    • Fail
  • completed every 1000 to 2000 hours blow out condenser coil(s). Also clean off any dust or debris build up.

    • Pass
    • Flag
    • Fail
  • completed every 1000 to 2000 hours check suction pressure.

    • Pass
    • Flag
    • Fail
  • First of the month, for units with built-in dryer: Inspect condenser of dryer and clean if necessary. Press the button on top of the electronic water drain (EWD). Clean the filter inside the EWD.

    • Pass
    • Flag
    • Fail
  • Quarterly first of the month. Remove the air filter element and inspect. Replace damaged or heavily contaminated elements.

    • Pass
    • Flag
    • Fail
  • completed every 4000 hours or every 12 months Replace related Pre & Post Line Filtration Elements.

    • Pass
    • Flag
    • Fail
  • Check readings on display, write down any alarms.

    • Pass
    • Flag
    • Fail
  • Check that condensate is discharged during operation.

    • Pass
    • Flag
    • Fail
  • Check the pressure dew-point temperature (compressors with integrated dryer).

    • Pass
    • Flag
    • Fail
  • Check the pressure dew-point temperature (compressors with integrated dryer).

    • Pass
    • Flag
    • Fail
  • Checking intake vents.

    • Pass
    • Flag
    • Fail
  • Clean the Air Filters weekly.

    • Pass
    • Flag
    • Fail
  • Check for any Pipe Blockage or Contamination verify by checking that pressures are within normal operating range.

    • Pass
    • Flag
    • Fail
  • Check for oil/air leaks.

    • Pass
    • Flag
    • Fail
  • Check Amps and Voltages when down.

    • Pass
    • Flag
    • Fail
  • Check Amps and Voltages when down.

    • Pass
    • Flag
    • Fail
  • Check for excess Vibration of parts.

    • Pass
    • Flag
    • Fail
  • Ensure that compressor cool down without any obstructions to the vents or filters.

    • Pass
    • Flag
    • Fail
  • Check for any visual signs of damage to your machine

    • Pass
    • Flag
    • Fail
  • Check for any external factors that will impact operations? (Water on the floor, dust in the air, excessive humidity)

    • Pass
    • Flag
    • Fail
  • Check that the guards are in the correct position

    • Pass
    • Flag
    • Fail
  • Make sure air receiver and dryer operational

    • Pass
    • Flag
    • Fail
  • Make sure air receiver and dryer operational

    • Pass
    • Flag
    • Fail
  • IMPORTANT NOTICE: FILTER CHANGE PERIOD IS 4000 HOURS GENERAL MAINTENANCE PERIOD IS 20 000 HOURS

    Source: MaintainX (Community Member)

    Please note that any procedure, checklist, or other document available in the MaintainX Global Procedure Library is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.