Back

Permit Audit & Completion

This procedure is used to audit permit-controlled work and formally close or cancel the permit once the job is complete.
Manaaki Whenua Landcare ResearchI
03/23/2026

Permit Audit & Completion

This procedure outlines the audit and closure of a permit-controlled job so the permit can be formally closed or cancelled. It guides the permit issuer and receiver through confirming the work site inspection, recording the closure or cancellation reason, verifying isolations and tools are cleared, confirming the site is clean and safe, notifying stakeholders, and signing off.

    Audit

    Contractor's Health & Safety measures in line with Permit conditions

    • Pass
    • Flag
    • Fail

    Permit Closure

    Only to be completed when the permit is closed or cancelled

    This permit is being

    if the answer is "oneOf [Cancelled]"

    Enter reason for cancellation

    All isolations have been removed

    • Yes
    • No
    • N / A

    Tools etc have been removed/accounted for

    • Yes
    • No
    • N / A

    The worksite has been left in a clean and safe condition

    • Yes
    • No
    • N / A

    Stakeholders have been notified

    if the answer is "oneOf [Yes]"

    Permit Receiver Signature

    Click here to sign

    Permit Issuer Signature

    Click here to sign
Source: Manaaki Whenua Landcare ResearchI (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.